[LDES-coremodel] [LDES] updates on RPS and carbon cap tasks

Kenji Shiraishi kenjis at berkeley.edu
Sun Feb 7 18:26:52 PST 2021


Hi Julia,

I have reflected the ITC and PTC extensions for solar and wind in the
attached cost file. Please let me know if you have any questions.

Also, after my review of transmission literature, I found that the
transmission costs that we can easily use for the input for SWITCH model
are the bulk transmission costs from the ReEDs document.
345 kV: $1,449/MW-km
500 kV: $837/MW-km
765 kV: $870/MW-km
(all the numbers are in $2010)
1) within California, multiply 2.25 with the number above.
2) between California and other WECC states, multiply 1.125 with those
numbers.
3) within other WECC regions, use the transmission costs as they are.
(page 54 of https://www.osti.gov/biblio/1606151)

Recent transmission expansions in California are the Tehachapi Renewable
Transmission Project. This project costs fit with the number above very
well.
Tehachapi: $2.0 billion/173miles/4,500MW = $1,596/MW-km (500kV)

The costs I reported in the previous meeting from EIA and NREL were the
costs of spur lines, not bulk transmissions. So they are rather connection
costs, not bulk transmission costs. I am sorry for causing confusion.

Best regards,
Kenji


On Sat, Feb 6, 2021 at 10:29 PM Sarah Kurtz <skurtz at ucmerced.edu> wrote:

> Thank you for the update and for doing the work, Julia!  This sounds like
> great progress!
> I look forward to hearing the results of the detective work next week - I
> hope the clues turn out to be easy to spot!
>
> Sarah
>
> On Feb 6, 2021, at 10:24 PM, Julia Szinai <jszinai at berkeley.edu> wrote:
>
> Hi team,
> I went through the current RPS policies state-by-state and updated the
> percentages for the SWITCH baseline input files. I made some
> simplifications because some states have different criteria for applying
> the RPS (by number of customers, utility type, load size, etc.) which don't
> correspond neatly with our load zone boundaries, but since it's really the
> carbon cap that is the binding constraint, these simplifications shouldn't
> matter.
>
> I wrote up the policies and SWITCH implementation here
> <https://docs.google.com/document/d/1YZwKxv8_WFYBBP5WauEnpXcCGrrn31Jy-kdYEY1xo5o/edit>,
> and have attached the CSV of the data I added to the db. I also added the
> new carbon cap scenario to the db (WECC cap: 80% of 1990 levels by 2050,
> subtracting the carbon cap of CA each year, and CA cap: 0% carbon by 2045).
>
> One of the next things on my to-do list was to update the renewable costs
> to include the PTC extension. Kenji, could you please send the update cost
> time series when you get a chance?
>
> I'm also meeting with Paty early next week to work on figuring out the
> solar candidate capacity discrepancy.
>
> Best,
> Julia
> --
> *Julia Szinai*
> PhD Candidate | Energy & Resources Group | University of California,
> Berkeley
> Graduate Student Researcher | Lawrence Berkeley National Lab
> NSF InFEWS Fellow
> Energy & Resources Group, MS '17
> Goldman School of Public Policy, MPP '17
> University of California, Berkeley
> jszinai at berkeley.edu
> <rps_scenario_id_7_new.csv>_______________________________________________
> LDES-coremodel mailing list
> LDES-coremodel at lists.ucmerced.edu
> https://lists.ucmerced.edu/mailman/listinfo/ldes-coremodel
>
>
> _______________________________________________
> LDES-coremodel mailing list
> LDES-coremodel at lists.ucmerced.edu
> https://lists.ucmerced.edu/mailman/listinfo/ldes-coremodel
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.ucmerced.edu/pipermail/ldes-coremodel/attachments/20210207/aefde26f/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: switch_costs_1_ptcitx_3.csv
Type: text/csv
Size: 12573 bytes
Desc: not available
URL: <http://lists.ucmerced.edu/pipermail/ldes-coremodel/attachments/20210207/aefde26f/attachment-0001.csv>


More information about the LDES-coremodel mailing list